This project was completed on 28th September.
What are we doing?
Remove the existing one pan toilet and replace with two pan toilet block. Design for access and mobility. To provide the public / community a more convenient 2 pan toilet and easier accessible entrance. Easier to clean.
Why are we doing it?
The existing toilet is out of date and very hard to clean. The current capacity is one pan (One Toilet)and with increased
demand in the community there is a need to increase the capacity to two pans.(Two Toilets) The current facility has electronic
controls including an electric door which has failed a number of times locking users inside.
How will it affect me?
· Toilet may be closed during replacement construction period.
· Replacement toilet will be on site during construction
Current Status: Toilet is ordered and due to be delivered in June 2023 ready to install end of June 2023
Start Date: June 2023
End Date: July 2023