Timeframes for processing resource consents

The Resource Management Act sets the number of working days that are allowed for each step of processing and making decisions on resource consent applications.

Due to current staff shortages we are experiencing delays in processing resource consents.

We are facing delays in processing applications due to current staff shortages.
The information below is based on the expected statutory timeframes under the RMA.

Pathways and timeframes are different depending on the type of consent and how complex it is. The decision as to what type of pathway an application needs to follow sits with the Council.

Fast track consents

Your consent application is fast-tracked if it meets the following:

  • It is for a district land use activity
  • It has 'controlled activity' status
  • You have provided an email address for communications
  • The Council decides that there's no need for public notification.
What the Council must do The expected time limit
Check an application is complete 5 working days from the date an application is received
Make a decision 10 working days from the date a complete application is received

Non-notified consents

A non-notified consent means that the Council has determined there is no need for public consultation, and/or all affected persons have given approval.

What the Council must do The expected time limit
Check an application is complete 10 working days from the date an application is received
Make a decision 20 working days from the date a complete application is received

While we are experiencing significant staff shortages the Council has doubled these timeframes.

Limited notified consents

A limited notified consent means that affected persons have a chance to have their say on how they believe the proposal will impact them. We identify who is affected, and must consider a person affected if the advere effects on them from the activity, if allowed, is going to be at least "minor".

What the Council must do The expected time limit
Check your application is complete 10 working days from the date your application is received
Advise affected persons that they can make a submission 20 working days from the date a complete application is received
Receive submissions 20 working days from the date affected persons were advised
Make a decision if there's no hearing 20 working days from the date submissions close
Close a hearing 45 working days after close of submissions
Release a decision after close of hearing 15 working days from the date the hearing closes

Publicly notified consents

A publicly notified consent means that the Council is seeking input from the public.

Generally, we do this when the rules in the TRMP let us, and if we think the effects on the environment are likely to be more than minor.

By notifyng the application and letting people have their say, their participation can provide useful evidence that make the final decision better. 

What the Council must do The expected time limits
Check an application is complete 10 working days from the date an application is received
Advertise in a public newspaper 20 working days from the date a complete application is received
Receive submissions 20 working days from the date the application is publically notified
Make a decision if there's no hearing 20 working days from the date submissions close
Close a hearing 75 working days after close of submissions
Release a decision after close of hearing 15 working days from the date the hearing closes